Chiswick Roundabout M4 elevated section roadworks March – November 2026
M4 elevated section by Chiswick Roundabout; Photograph Anne Marshall
Roadworks beginning Monday 9 March
Roadworks will begin again soon to repair the concrete pillars of the elevated section of the M4 beside Chiswick Roundabout.
The works, on pillars one to 12, are currently expected to take place between March and November 2026, with the proposed start date of Monday 9 March 2026, though the dates remain subject to final approvals and may change.
To carry out the works safely, National Highways expect the following lane closure of the A4 Great West Road to take place:
Lane three of the A4 Great West Road will be closed 24/7 in both directions between the Chiswick Roundabout and Lionel Road North/South for the duration of the programme.
Additionally, a small number of overnight full closures of the A4 will be required to install and remove scaffolding. These are currently anticipated to take place in March and November.
All pedestrian crossings are expected to remain open throughout the work.