Hammersmith & Fulham Council wants TfL and Government to pick up their share of Hammersmith Bridge costs

Image: Hammersmith Bridge

Hammersmith & Fulham Council demand TfL and Government to ‘pay their share’ of stabilisation and restoration works

Hammersmith & Fulham Council says it wants the Government and Transport for London to cough up their share of the costs of stabilising and restoring Hammersmith Bridge.

Since the Grade II*-listed bridge closed in 2019, the Council has spent almost £48 million on stabilisation and pre-restoration works. A 2021 funding settlement with the previous Government determined that costs would be split evenly among the local authority, TfL, and the Department for Transport (DfT).

According to a recent Council report, the DfT and TfL have so far contributed £8.3 million and £2.9 million respectively towards the total expenditure. The Council is now seeking to recoup some of its costs, and is demanding the Government and TfL pay their share.

A spokesperson for H&F Council said: “We meet regularly with DfT and TfL and expect them to meet the agreed contributions.”

The Hammersmith Bridge taskforce, which had not met in three years, was reconvened last week by Labour’s Minister for Local Transport, Simon Lightwood.

A DfT spokesperson contested the Council’s figures, saying the department had provided £13 million for the bridge. However, the Council maintains that only £8.3 million of this is directly related to stabilisation and restoration.

Both the DfT and TfL have provided ambiguous responses regarding the £20.7 million claim. It is understood that the DfT has not yet received a formal request from the Council for reimbursement.

TfL, which has contributed just under £3 million to stabilisation works, stressed its ongoing support for the project. It pointed out that beyond this sum, it has spent £16.7 million on refurbishment planning, including assessments, feasibility studies, inspections, surveys, and design work.

Image: Hammersmith Bridge in August 2020; Photograph The Chiswick Calendar library

“It was a good meeting” – Andy Slaughter MP

Hammersmith and Chiswick MP Andy Slaughter was upbeat about the taskforce meeting, telling The Chiswick Calendar “it was a good meeting.”

Despite any potential frostiness over who would be paying what, he said the meeting was cordial and there were some good things that came out of it.

Firstly, the three parties have agreed to commission a set of traffic figures on which they can all agree to give them a working indication of how much traffic can be expected to cross the bridge when it reopens.

Secondly, they have narrowed the options for the bridge’s future to three: keeping the bridge and reopening it either for pedestrians, cycles and some wort of mobility transport only; making it capable of carrying single decker buses in addition; or with single decker buses and cars in addition, dispensing with some of the outliers amongst previous options, such as demolishing the bridge altogether and building a new one, or keeping it merely as a monument.

Thirdly, they are now looking at ways of keeping the cost down, such as using cheaper materials instead of replacing the cast iron and wooden structure with like for like materials.

Almost six years since bridge closed

The 138-year-old bridge, connecting Hammersmith with Barnes, initially closed to motor vehicles in April 2019 after micro-fractures were discovered in its pedestals. All users were barred in August 2020 due to safety concerns, but the bridge has since reopened for pedestrians, dismounted cyclists, and river traffic.

The projected cost of fully repairing and reopening the bridge has escalated to an estimated £250 million and additional phases of work are required. Hammersmith & Fulham Council, which owns the bridge, insists a toll will be necessary to fund its share of the costs.

The DfT has signalled that given financial constraints, any funding solution must involve an appropriate cost-sharing arrangement. Further government funding hinges on an agreement covering both engineering requirements and financial commitments.

The Council submitted a business case for restoring and reopening the bridge to the previous Government in December 2022, formally presenting it in March 2023. Approval remains pending.

In a report prepared for a Cabinet meeting on Monday (10 February), council officers said: “The Council is therefore due a further total of £20.7m from DfT and TfL and is requesting that the previously agreed contributions are paid up in full.”

The report also reaffirmed the necessity of a toll, noting that while the relevant government minister had expressed support for such a scheme, backing from TfL and DfT has yet to materialise.

Image: Hammersmith Bridge restoration project team in 2022; Photograph The Chiswick Calendar library

DfT and TfL say they continue to “work closely” with H&F Council

A DfT spokesperson said:

“The London Borough of Hammersmith and Fulham is responsible for the operational and maintenance costs of the bridge as the asset owner.

“We continue to work closely with the London Borough of Hammersmith and Fulham and Transport for London on exploring options for the future of the bridge and the department has provided £13m of funding towards the project so far.”

A TfL spokesperson said:

“We have been actively supporting the London Borough of Hammersmith and Fulham and we will continue to work closely alongside the Department for Transport, the borough and other stakeholders on the Hammersmith Bridge Taskforce to agree the right solution, which includes ongoing discussions on how future work on the bridge might be funded.”

Any capital programmes, such as Hammersmith Bridge, are expected to be made after Chancellor Rachel Reeves’s Spring Spending Review.