If Hammersmith Bridge doesn’t get Government funding it will close, says LB Hammersmith & Fulham officer

Hammersmith Bridge; photograph LB Hammersmith & Fulham

As Hammersmith & Fulham Council waits to hear whether they will receive Government funding for Hammersmith Bridge, Mark Averill tells London Assembly the bridge will close without it

If LB Hammersmith & Fulham do not get £128m from the Government’s ‘Structures’ fund, Hammersmith Bridge will deteriorate to the point where it will not even be able to be used by cyclists and pedestrians.

At a meeting of the Transport Committee of the London Assembly on Tuesday (3 November) to discuss London’s river bridges, Mark Averill, Interim Assistant Director Highways at the London Borough of Hammersmith & Fulham was asked what would happen if they did not receive the money they have bid for from the Structures fund to repair Hammersmith Bridge.

He answered that the bridge would continue to deteriorate gradually to the point where the main carriageway would have to close to cyclists, and eventually to the point where the Council would have to close the pedestrian walkways on the sides of the bridge as well.

“Without that it can only get slowly worse”, he said, despite a regular programme of maintenance which involved cleaning and greasing the bearings which were accessible. This year the Council has spent £1.1m on that regular maintenance.

Vauxhall Bridge

Thames crossings in a sorry state

The Transport Committee, chaired by Caroline Russell AM, discussed the condition of the Thames road bridges.

Hammersmith Bridge has been closed to vehicles for more than seven years, since April 2019.

Albert Bridge is also closed to motor traffic at the moment. Another historic piece of Victorian engineering, Albert Bridge has been closed to motor traffic since February, when a routine inspection found a crack in a cast iron component at one of the bridge abutments.

Vauxhall Bridge currently has a weight restriction on it of 18 tonnes, introduced in July owing to a recent assessment which showed elements of the structure have recently deteriorated.

That weight restriction is now having an impact on Chelsea Bridge, Andrew Burton, Director of Highway and Regulatory Services, Royal Borough of Kensington and Chelsea told the meeting, as more heavy vehicles are crossing the river there instead.

 

Albert Bridge; photograph LB Kensington & Chelsea

Albert Bridge closed to pedestrians Saturday 7 and Sunday 8 November

Albert Bridge was closed even to pedestrians for a 48-hour unplanned period over the summer because of the effect of the extreme heat on the bridge, and it will be closed again to pedestrians on Saturday 7 November from 7.30pm to 10pm and Sunday 8 November from 6.00 pm to 8.30pm to manage crowds attending nearby firework displays.

It will cost £8.5m to fix. Kensington & Chelsea have committed to do the work whether or not they receive grant money from Transport for London and the Government, Andrew Burton told Assembly Members, and they expect to have the bridge open again at some point next year.

One of the problems all the bridges face is that cars are getting heavier. When the Transport Committee looked at the state of Thames bridges last, five years ago, the average weight of a car was 1.5 tons, whereas now it is 2 tons. As buses are converted to run on batteries they are also getting heavier.

Satbir Gill, Chairman of the London Technical Advisors Group, told the meeting that of the 30 structures crossing the Thames in London, 16 were in “poor” or “very poor” condition. Only six were in “good” or “fair” condition.

City Bridge Foundation ongoing programme of maintenance on Tower Bridge; photograph City Bridge Foundation

No overall plan for investment in London bridges

Simon Latham, Managing Director of the City Bridge Foundation, was asked about his organisation’s model of funding. The City Bridge Foundation is a charity which looks after five bridges: Tower Bridge, London Bridge, Southwark Bridge, the Millennium Bridge and Blackfriars Bridge.

They have an ongoing 50-year repair and maintenance scheme, he said, and all of their bridges are currently safe and in good condition. Blackfriars Bridge is currently undergoing major refurbishment which requires lane closures overnight.

Their money comes from an endowment invested in property and financial instruments which bring them an income.

The committee discussed whether a scheme for the whole of London would be feasible – whether all boroughs could be persuaded to put into a pot which would benefit the whole of London but would effectively provide heavy subsidise for only a few of them.

Currently fifteen of the bridges are the responsibility of individual boroughs, while ten are the responsibility of Transport for London and five the responsibility of the City Bridge Foundation.

Mark Averill, for Hammersmith & Fulham, said the current Department for Transport system for funding regular maintenance worked well, supporting good asset management, but the system for applying for large capital grants for big projects did not.

They had to spend a huge amount of money on consultants each time they applied for grants, he said, which they might not receive.

Hammersmith Bridge; photograph Bridget Osborne

Department of Transport due to make funding announcement ‘Autumn 2026’

LB Hammersmith & Fulham needs £128 million to replace the bridge deck bearings, the bearings in the towers and the hangers on Hammersmith Bridge.

The Council has applied to the Government’s Structures fund for the money to replace the bearings – from a £1bn pot of funds available for the whole country.

If they get it, they have to complete the work by March 2030, which would in itself be challenging, me told the London Assembly’s Transport Committee, as until they come to replace the bearings they do not know quite what they might find.

“Without that investment being made, the bridge will have to close”, he said.

Assembly Member Neil Garrett commented that even if they did get the £128m and they replaced the bearings, this would still only be a “patch-up job”. He asked whether the Council had considered replacing it with a new one.

Mark Averill replied: “That is not for me to say” and refused to be drawn further on whether the Council had looked into that possibility.

If they received the £128m they have asked for to replace the bridge’s bearings and hangers, this would keep it operational “for a good period of time”, he said – 20 years or so as it is now, just being used by cyclists and pedestrians.

The Department of Transport expects to make an announcement on the funding awards in ‘Autumn 2026’.