Piccadilly Line upgrade weekend closures December – January
New trains commissioned for the Piccadilly Line; Siemens
Series of part closures on Piccadilly Line to facilitate work to get it ready for new and better trains
There is a programme of part-closures of the Piccadilly Line throughout the winter as Transport for London gets the line ready to take the new, improved trains it has bought from Siemens.
Eventually we will see the gain, but right now we are experiencing the pain. The closures are scheduled to take place at weekends:
Saturday 6 – Sunday 7 December – Acton Town to Uxbridge (also Metropolitan line closure)
Friday 2 January (Night Tube) – King’s Cross St Pancras to Cockfosters
Saturday 3 – Sunday 4 January – Wood Green to Cockfosters and Rayners Lane to Uxbridge
CGI of upgraded Piccadilly Line facilities
New trains, new depots and sidings, and adjustments to platforms
Londoners and visitors take around 158 million trips annually on the Piccadilly Line. TfL received the first of the new fleet of state-of-the-art trains a year ago that they promise will greatly improve the experience of customers.
They are gradually introducing the new trains over the next few months, but first of all need to make adjustments to platforms and track positions. At Cockfosters and Northfields they are also building new facilities with extra space to clean and care for them.
‘As well as adding new trains, we’ll also be upgrading ageing assets on the line’, say TfL. ‘The work will be done in stages across the line to help make sure it has a minimum impact on our customers’.
Originally the new trains were supposed to be in service by now, but once the engineers were able to see them in situ, they realised there was more work to be done to integrate them into the city’s elderly passenger network. In June TfL announced that they would not be in service until summer 2026.
READ ALSO: Introduction of new trains on the Piccadilly Line delayed by a year
A view inside the new trains
‘A better, greener and more reliable service’
When we do get to experience using them, we will discover the trains, developed by Siemens in Germany, will have walk-through carriages, air-conditioning – for the first time on a deep Tube train – wider all-double doorways to help customers get on and off more easily, and there should also be improved step-free access from/onto the platform.
The upgraded depots will be more eco-friendly, with green roofs that collect rainwater for washing trains and solar panels to help power the buildings.
‘This will mean a better, greener and more reliable service for our customers’.
Once the trains are in service they say they will ‘transform journeys for millions of customers’. They will offer 10% more capacity and are lighter than the existing design, which was introduced in the 1970s, which means they are more energy efficient and will provide a smoother ride for customers, consuming 20% less energy.
The power system on the Piccadilly line is also being upgraded, to ensure the new trains run ‘as reliably and efficiently as possible’ when TfL starts running more trains at the busiest times.
TfL is expecting to be able to run 27 trains an hour rather than the current 24 at peak times.