Repairs to the river wall at Strand on the Green make progress – on time and on budget

Tim Hurley, Service Director of Hounslow Highways

Service Director of Hounslow Highways Tim Hurley tells us how the repairs to the river wall are progressing

The repairs to the river wall at Strand on the Green are progressing on time and on budget, according to the Service Director of Hounslow Highways Tim Hurley.

Tim took the time to show The Chiswick Calendar what his team have been doing along Strand on the Green, from the beginning of the tow path on Grove Park Road to Kew Bridge.

It was five years ago that I first noticed a gap had opened up between the river wall and the towpath underneath the railway bridge beside the Bull’s Head. To the untutored eye it looked as if it could be dangerous.

READ ALSO: Gap opens up along the tow path at Strand on the Green

I noted at the time: ‘Not being an engineer I didn’t know if the wall was in danger of collapse or would stay like that for another hundred years, but I’m pleased to say when I reported it, Hounslow engineers acted on it straight away and are now monitoring it’.

Gap between the river wall and the towpath (L) May 2021; (R) October 2026

The wall underneath the railway bridge is leaning and needs pinning

“Cllr Guy Lambert [whose portfolio as Cabinet Member then included working with Hounslow Highways] was very proactive about it”, Tim told me.

Five years on, part of the programme of work they are doing at the moment includes pinning the wall, so it does not lean further out.

He confirmed it is leaning outwards (the gap is bigger than it was in 2021) but said they have tested the ground beneath the towpath and found it is solid concrete. Even if the wall were to fall over, it would not take the tow path with it and undermine the foundations of the bridge, he told me.

“We excavated a section. The original pins have deteriorated over time, probably with the vibration from the track, so we will pin it with lateral pins”.

They are not responsible for the railway bridge, which is also showing signs of wear and tear, with cracks up the wall supporting the bridge. That is being looked at separately by engineers from Network Rail.

(L) Stretch of the towpath they’re currently workking on; (R) stretch they have already done

A proper job

The work they are currently undertaking is a thorough job involving the replacement  of some bits of wall and the repair of other sections. It has taken this long because the towpath at Strand on the Green, even though technically a ‘highway’ was not part of their contract with Hounslow Council.

One of the positives to come out of this exercise, Tim told me, is that there were 13 sites which did not come under their remit, which now do, including Strand on the Green and also the towpath and wall at Chiswick Pier.

First of all they needed to ascertain the size of the problem:

“What has been interesting is finding out what we didn’t know about the river wall and understanding the issues”.

That took an initial inspection and then an in-depth inspection by specialists brought in to do the job.

The river wall in April 2024; photograph Ann Collins

Project Board includes Chair of Strand on the Green Association

The river wall is several hundred years old and consists of rubble mainly; brick in places, patched up with concrete over the years; edged with coping stones which have been loosened and shifted over time due to pressure from tree roots and weeds growing between the towpath and the edge, watered regularly by the tide.

Once they had an idea of the size of the problem, they then had to put together a budget for the work and have it signed off by the Council.

READ ALSO: Is the river wall at Strand on the Green in danger of collapsing?

READ ALSO: Hounslow Council commits to funding repair of river wall at Strand on the Green

They set up a Project Board in 2024 which included Chair of the Strand on the Green Association Ann Collins and Chiswick Riverside Councillor Gabriella Giles in her capacity as chair of the Thames Landscape Strategy.

“It’s unusual to include a resident, but it is important to include a member of the local community who has good knowledge and can provide historical information, drawings photographs, that all help build a picture”.

It now also includes Chiswick Riverside Councillor Amy Croft, Cabinet Member for Infrastructure at Hounslow Council, whose portfolio includes working with Hounslow Highways.

The section of the tow path which collapsed in December 2024

Emergency work needed in December 2024

Tim’s team had to carry out some emergency work in December 2024 when part of the wall collapsed near Compass House, which cost about £70,000.

READ ALSO: Emergency work starts on repairing the river wall at Strand on the Green

READ ALSO: Progress towards urgent work to mend river wall at Strand on the Green

They have to carry out what they call an “options analysis” – what is the risk and the cost if they do the least amount of work they can get away with, what is it if they do a thorough job that will last, and a third option somewhere between the two.

New steps to replace the rotten ones

Tim was pleased the Council opted to do the job properly and agreed a budget of £750,000 in April. So was Ann:

“The Council chose to do everything rather than just patch it up, rightly in my view”.

The work started in May and all through the heat of the summer you could see workmen sweltering in full high vis suits dodging the tides and working away at repairing the wall.

They are delivering the river wall repairs “on time and on budget”, he said, helped by the fact they had contingency budget in case they found they had to replace the whole towpath in the section where the river wall has parted company with the path, and as it has turned out they do not need it.

Subcontractors Top Bond working on the towpath

Repairs should be finished by Christmas

A company called Top Bond are the subcontractors, a leading specialist in marine, civil engineering, and waterway construction services across tidal and non-tidal rivers in the UK. One of the repairs clearly visible from the path is a new set of wooden steps down to the Strand to replace those that had rotted away near Ship Alley.

How long will the repairs last?

“I’d like to say forever. It depends on continued maintenance but it should last ten or twenty years, or longer”.

Weeds determindly growing wherever they can get a foothold

By “continued maintenance” he meant specifically keeping down the weeds. They cannot use chemicals by the river, so they are using some of the methods the Council has tried out while Glyphosate was banned, such as using a heat lance to stress the roots of weeds.

That is something Ann Collins is keen to see happen regularly and will make it her mission to monitor.

“We have an opportunity here”, she told me, as custodians of a lovely stretch of the river which many people come to enjoy.

“I’m proud of the work we’re doing here”. said Tim. “It’s a wonderful project”.

He expects the work to be completed by Christmas.

They have had plastic barriers washed away by the tide – or possibly pushed into the river – so they are now weighted down with sandbags